Project

Redevelopment of Culture and Education Area

Concrete Pump and Boom Pouring Concrete at sadder Down Town Project Under Pass.

1400 Nos Pilling of Complete Building Structure including 02 Story Basement Parking.

QKC executed specialized concrete pumping and boom pouring works at the Saddar Downtown Project Underpass. The scope included 1,400 nos piling for the complete building structure along with the construction of a two-storey basement parking facility. The project showcased QKC’s expertise in advanced construction techniques, delivering precision, durability, and efficiency in a high-density urban environment.

Client

Planning & Development Department,  Sindh

Location

Saddar Downtown Karachi, Sindh

Category

Development 

Cost

1672.285 Million